01What it is
A new order gets a number starting with ZAM and begins as a Draft. You choose an active supplier, the order date (not in the future) and, optionally, the project you are ordering for. Without a project the order goes to stock. You can enter an Expected delivery, but it cannot be earlier than the order date.
You add lines on the order card with the Add line action, choosing an active item from the materials and plants register. Each item can be on an order only once, and to change a quantity you remove the line and add it again. The price of a line is the purchase price from the register, unless you enter another one with the Finance permission.
You can Send to supplier an order that has at least one line and whose expected delivery is not in the past. You cannot edit a sent order. You can Cancel a draft or a sent order, but you can delete only a draft. A sent order is cancelled and its history stays.
You receive a delivery with the Receive delivery action on a line of a sent order. You enter the quantity received (no more than what is still due), the date received (not in the future) and, with the Finance permission, the net price. A Receipt movement is created in stock, and the order changes its status to Partly received or Received. When the supplier will not deliver the rest, use Close with shortfall: the order becomes Received and the shortfall is recorded in the activity log.
- STATUSES
- Draft, Sent, Partly received, Received and Cancelled.
- OVERDUE
- A sent or partly received order past its date shows overdue in the list and appears on the dashboard as Late deliveries.
- RECEIVING
- In full or in parts, each with a Receipt movement in stock.
- DELETION BLOCKS
- You cannot delete a supplier, a register item or a project that has an order.
02Tasks step by step
- STEP 1Open Modules › Resources › Orders.
- STEP 2Choose New order.
- STEP 3Choose the supplier and enter the order date and the expected delivery. If you are ordering for a particular project, choose it in the Project field.
- STEP 4Save the order. Its card opens.
- STEP 5Choose Add line, choose an item from the register, enter the quantity and save. Repeat for further lines.
- STEP 6Choose Send to supplier.
- STEP 1Open the card of a sent order from the Orders list.
- STEP 2On the line, choose Receive delivery.
- STEP 3Keep the proposed quantity or enter a smaller one that was actually delivered.
- STEP 4Check the date received and, with the Finance permission, the net price per unit.
- STEP 5Save. The stock of the item goes up and the order status changes to Partly received or Received.
- STEP 1Open the card of an order with the status Partly received.
- STEP 2Choose Close with shortfall.
- STEP 3Check that the order now has the status Received. The shortfall is recorded in the activity log.
- STEP 1Open the Dashboard and find the Late deliveries item.
- STEP 2Select it to see the orders whose delivery date has already passed.
03What it connects to
Catalogue
Items and suppliers that you order from.
Go to the topicCatalogueStock and batches
A Receipt movement raises the stock of the item.
Go to the topicStock and batchesUsage and costs
The delivery price becomes the purchase price used in costs.